ICRD Construction Projects

2016 Active Remaining Projects:   

Holt Road; Grovenburg Rd to Aurelius Rd (Delhi Twp)Construction work including asphalt resurfacing, traffic signal and sidewalk is substantially complete.  A surface sealer will be applied between Eifert Rd and Aurelius Rd in the spring of 2017 (intermittent lane closures should be expected).  Optimization of new traffic signals is in progress.

Park Lake Road; Grand River Avenue to Merritt Rd (Meridian Twp)Construction work including asphalt resurfacing and widening for LT turn lane N of Haslett Road substantially complete.  Minor traffic and pedestrian signal work at Haslett Rd intersection remain to be completed in the spring of 2017 (intermittent lane closures on Haslett Rd should be expected).

Hagadorn Road; Mt. Hope intersection (Meridian Twp) Construction work to widen and resurface intersection is substantially complete.  Minor turf restoration and project cleanup work remaining (intermittent lane closures and/or traffic regulator control should be expected).

Haslett Road; Williamston Rd to M-52 - Preventative maintenance resurfacing completed.  Guardrail replacement to be completed spring 2017 (intermittent lane closure with traffic regulator control should be expected).


2017 Projects

Listed below are projects scheduled to be constructed during the 2017 and/or 2018 construction season (note: information is subject to change and will be periodically updated as these projects progress):

Cedar Street; Legion Drive to College Road (Alaiedon, Delhi, and Vevay Twps.) Rehabilitation and resurfacing existing concrete four lane divided highway by rubblizing existing concrete pavement in-place and repaving with asphalt.  This project also includes culvert/storm sewer replacement and crossover construction.  This project will begin on Monday, May 8th.  The proposed work includes in-place crushing and recycling of the existing concrete pavement into base material and asphalt resurfacing of the four lane divided highway. Traffic will be maintained with one lane in each direction along the entire project.  Access will be maintained to all adjacent properties throughout construction. During large portions of the construction, traffic will be shifted via temporary cross-overs, to one side of the divided highway, then the other, while the opposing side is recycled and resurfaced.  As part of the project, the various existing median cross-overs will be consolidated into one-way, indirect left turns with deceleration lanes for improved safety. The project will also include paved shoulders and drainage upgrades.  Project completion is expected in early October dependent on weather and any other unforeseen circumstances.

Okemos Road; Jolly Rd Intersection (Meridian & Alaiedon Twps) - Intersection reconstruction and widening for RT turn lanes, including concrete overlay pavement construction (Okemos Road), asphalt paving (Jolly Road), storm sewer, curb and gutter, sidewalk, and new traffic signal construction.  A June 2017 bid letting is anticipated, as well as for construction to begin in July 2017.  Motorists should expect multiple lane closures and traffic phasing during construction.  Left turns will be prohibited at the intersection, so all turning traffic will be detoured.  Use of alternate routes will be suggested.

Holt Road; Depot Street to US-127 (Delhi Twp) Asphalt resurfacing, with widening and restriping for LT turn lane and new traffic signal construction at College Road intersection.  RT turn lanes will be constructed on all approaches, and College Rd approaches will be restriped for center LT turn lane.  Spring/summer 2017 Construction anticipated.  Traffic will be maintained with lane closures and traffic regulator control during construction.

Fitchburg Road; Leslie City Limits to Nims Road (Leslie & Bunker Hill Twps) 4.3 miles of HMA patching and resurfacing, along with machine grading, intersection curb and gutter, aggregate shoulders, slope restoration, and pavement markings.  Trees too close to the road will be removed to improve the safety clear zone.  A June 2017 MDOT bid letting is anticipated with construction to take place later in summer 2017 for MDOT contracted work.  Traffic will be detoured via Kinneville Road during replacement of several culvert crossings.  Traffic will be maintained with lane closures and traffic regulator control during the remainder of construction operations.

Sherwood Road; Zimmer Road to Williamston Road (Williamstown Twp) Asphalt resurfacing with chip seal interlayer, and culvert/sewer crossing replacements.  Trees too close to the road will be removed to improve the safety clear zone.  Spring/summer 2017 Construction anticipated.  Traffic may be detoured for culvert and storm sewer construction, and maintained with traffic regulator control during remaining construction operations.

Elm Road; I-96 to Grand River Avenue (Leroy Twp) - Asphalt resurfacing with chip seal interlayer, and culvert/sewer crossing replacements.  Trees too close to the road will be removed to improve the safety clear zone.  Spring/summer 2017 Construction anticipated.  Traffic may be detoured for culvert and storm sewer construction, and maintained with traffic regulator control during remaining construction operations.

Zimmer Road crossing the Deer Creek (Wheatfield Twp)Bridge Replacement with prefabricated concrete arch culvert with approach reconstruction. This project was bid and awarded to Davis Construction of Lansing.
Spring/summer 2017 Construction anticipated.  Zimmer Road will be closed during construction; all traffic will be detoured.  

Columbia Road crossing the Grand River (Aurelius Twp) Replace 3 span bridge with single span steel truss bridge with approach reconstruction.  Fall 2017/Spring 2018 Construction anticipated.  Columbia Road will be closed during construction; all traffic will be detoured.

Jolly Road; Dobie Rd to Meridian Rd (Meridian & Alaiedon Twps)Asphalt recycling, widening for paved shoulders, and resurfacing, including grading and drainage improvements, and culvert replacements (includes 2 large culverts E & W of Every Road, requiring full closure to traffic and detour).  Trees will be removed as required for grading and clear zone safety improvements.  Winter 2017/Spring 2018 Construction anticipated.


2018 Projects: Funding TIP Total Match
Olds Road Bridge over Perry Creek (rehabilitation) Local Bridge $210,000 $ 11K
Olds Road Bridge over Huntoon Creek (rehabilitation) Local Bridge $210,000 $ 11K
Howell Road Bridge over Doan Creek (rehabilitation) Local Bridge $305,000 $ 15K
Lake Lansing Road – Hagadorn Road to I-69 BR (resurface) Urban STP $600,000 $120K
Countywide Rural Road Improvements Rural STP & D $492,448 $ 99K
       
2019 Projects:
Okemos Road – Shawnee Trail to Clinton Street (reconstruct) STPU & NHPP $3,200,000 $1.94M
NOTE: The $1.94M of match for Okemos Road will likely be offset by Local Bridge Program funding.
Waverly Road – Lansing Road to St. Joseph Street (resurface) Urban STP $600,000 $120K
Countywide Rural Road Improvements Rural STP & D $718,750 $144K
       
2020 Projects:
Cedar Street – College Road to Circle Drive (resurface) Urban STP $1,121,046 $225K