ICRD Construction Projects

2018 Projects 

Cedar Street, Holt to Aurelius Roads, Delhi Township –  To be reconstructed in phases starting May 14th.  Project designed and being constructed and managed by Delhi Township.  For more information please click on the following:  Realize Cedar Information

Urban Primary Road Resurfacing – In place pavement recycling, asphalt resurfacing and drainage improvements. Projects listed below will begin week of September 4, 2018, and will be completed by mid to late October 2018 unless otherwise noted below. Traffic will be affected as shown below. 

Cedar Street – Aurelius Road to Willoughby Road, resurfaced in conjunction with Cedar Street, Holt to Aurelius, shown above.  Resurfacing Cedar Street, Aurelius Road to Willoughby Road, has been completed.

Hagadorn Road – Jolly Rd to approximately 2000 feet south of Mt Hope Rd.  Project is substantially complete. Only turf restoration remains. The remaining work will be performed under traffic regulator control. 

Wood Street – Grand River Avenue to Lake Lansing Road.  Traffic will be maintained with various lane restrictions.
Lake Lansing Road – Lansing City Limits to Wood Street.  Traffic will be maintained with various lane restrictions.

Haslett Road – RR Tracks to Creekwood Drive, East of Van Atta Road.  Traffic will be maintained with various lane restrictions. 

Eifert Road  -  Holt Road to Willoughby Road.  Project is substantially complete. Only shoulder restoration remains. The remaining work will be performed under traffic regulator control. 

Mitchell Road – Williamston Road to Vanetter Road. Traffic will be maintained with various lane restrictions.  Work expected to start mid-September. 
Vanneter Road – Mitchell Road to Rowley Road.  Traffic will be maintained with various lane restrictions.  Work expected to start mid-September. 

Hamilton Road – East and west ends at Grand River (M-43) to and including Nakoma Street intersection on west end and including Dobie Road intersection on east end.  Traffic will be maintained with various lane restrictions.  Work expected to start mid-September. 
         

Rural Primary Road Resurfacing –  In place pavement recycling, asphalt resurfacing and drainage improvements. Projects began in early July and will be completed in early October. Through traffic will be detoured per posted routes for certain periods. Local access will be maintained at all times from one end or the other per sequential moving closures.

Haslett Road – M-52 to Morrice Road
Fitchburg Road – Nims Road to Freiermuth Road
Williamston Road – West Road to Howell Road


Bridge Projects –  Projects will take place in Fall of 2018 or Spring of 2019. Traffic will be detoured per posted routes.

Olds Road Bridge over Perry Creek – Replace structure. 
Olds Road Bridge over Huntoon Creek –  Replace structure. 
Howell Road Bridge over Doan Creek –  Replace deck and rail. 


2018 Chip-Sealing – Our chip sealing crew is currently on hold due to weather. 

The following is a list of county roads to be chip sealed. Please be aware this list is subject to change depending on the needs of other road projects, detour routes, and inclement weather.

   Roads are temporarily closed to traffic for approximately several hours only at time of chip-sealing a given mile.

Alaiedon Twp.

Okemos Road – Holt to Mason City limits
Stillman Road – Meridian to Sandhill/Dobie
Lamb Road – Hagadorn to Walline
Harper Road – Okemos to Wolverine
Wolverine Road – Harper to Howell
Sandhill Road – College to Okemos
Hagadorn Road – Howell to Mason City limits  

Aurelius Twp.

Columbia Road –College to Onondaga
Eifert Road – Toles to Bunker
Eifert Road – Columbia to Nichols

Bunker Hill Twp.

Parman Road – Ewers to Fitchburg
Williams Road – Ewers to Decamp (Double application of Chip seal)
Catholic Church Road – Williamston to Murry
Freiermuth Road – Decamp to Fitchburg
Baseline Road – Bunkerhill to Freiermuth
Williamston Road – Bunkerhill to Catholic Church
Decamp Road – Williams to Haynes                                                                        

Delhi Twp.

Bishop Road – Waverly to M-99
Holt Road – Waverly to Grovenburg
Grovenburg Road –Nichols to Bishop
Eifert Road – Nichols to McCue
Nichols Road – Onondaga to Grovenburg
Depot Street – Holt to Keller
Waverly Road – M-99 to Bishop                                                                                

Ingham Twp.

Osborne Road – Howell to Columbia
Dexter Trail – Carter to Murry                                                                                   

Leroy Twp.

Elm Road – M-43 to Townsend                                                                                 

Leslie Twp.

Blackmore Road – Bellevue to Kinneville
Covert Road – US-127 to Aurelius
Jackson Road – Baseline to Fitchburg
Fitchburg Road – Leslie limits to 1,500 feet east of Nims
Ingalls Road – Hull to Eden
Oak Street – Kinneville to Leslie City limit
Main Street – Hull to Leslie City limits
Dutch Road – Baseline to Olds
Hull Road – Bellevue to Covert                                                                                  

Locke Twp.

Morrice Road – County line to Haslett
Rowley Road – Dietz to M-52                                                                                     

Meridian Twp.

Cornell Road – Orlando to M-43
Bennett Road – College to Okemos                                                                        

Onondaga Twp.

Aurelius/Byrum Road – Barnes to Bellevue
Kinneville Road – Waverly to Onondaga                                                                               

Stockbridge Twp.

Brogan Road – M-36 to M-106
Dexter Trail – Brogan to County line
Adams Road – Dexter Trail to Morton
Chapman Road – Catholic Church to Obrien                                                        

Vevay Twp.

Columbia – College to Mason City limits
Eden Road – Rolfe to Barnes
Tomlinson Road – Tuttle to Service
Kipp Road – Tuttle to US-127
Sitts Road – College to Mason City limits
Howell Road – College to Okemos                                                                           

Wheatfield Twp.

Linn Road – Meridian to Williamston City limits
Noble Road – Meridian to Burkley
Zimmer Road – Holt to Waldo
Williamston Road – I-96 to Howell
Corwin Road – M-43 to Gravel                                                                                  

White Oak Twp.

Dietz Road – Columbia to Iosco
Carter Road – Proctor to M-52     

Williamstown Twp.

Turner Road – Meridian to Burkley
Shoeman Road – Haslett to The county line
Gulick Road - Shoeman to Zimmer
Barry Road – Shoeman to Lounsbury
Zimmer Road – Haslett to RxR
Sherwood Road – Zimmer to Williamston

                                                                             

Completion of 2017 Projects

Projects listed below were started in 2017 and will be completed during the 2018 construction season (note: information is subject to change and will be periodically updated as projects progress):

Okemos-Jolly Intersection (Meridian & Alaiedon Townships) Intersection reconstruction and widening for right turn lanes on northbound, eastbound, and southbound approaches, including concrete pavement overlay, storm sewer, curb and gutter, sidewalk, and new traffic signal.  Work has been substantially completed on this project.  Minor clean-up and restoration remains to be completed in fall 2018 which may include brief outer lane closures around the given work.  Click on project name in blue text for more information. 

Jolly Road; Dobie Rd to Meridian Rd (Meridian & Alaiedon Townships) – 2.4 miles of asphalt recycling, widening for 4 foot wide paved shoulders, grading, and asphalt paving.  Also included two large culvert replacements near Every Road, and minor grade changes to improve sight distance,  Click on project name in blue text for more information and detour routes. 
Work on this project has been completed through first layer of asphalt.  Second layer of asphalt, shoulders and other restoration is expected to be completed in fall 2018, see NOTE below.  Signs are posted to indicate the road remains closed to through traffic, however traffic may access all destinations within the closure and may pass through when work is not occurring, however will need to use the posted detour route when work is occurring to reach destinations beyond the point at which work is occurring at a given time.
NOTE:  Work has stopped on the Jolly Road project, Dobie to Meridian Roads, due to the current statewide labor dispute between contractors affiliated with the Michigan Infrastructure & Transportation Association (MITA), which includes the contractors on the Jolly Road project, and construction equipment operators represented by the Operations Engineers Local 324 union.  Future updates will be provided here when available.

Columbia Road crossing the Grand River (Aurelius Twp) – Bridge replacement substantially complete. An actuated yellow flasher system will be installed to assist drivers with identifying approaching traffic. That work is expected to occur in October with shoulder and/or lane closures (traffic regulator control) only; the bridge will remain open to through traffic.

South Waverly Road at Columbia Road visibility concern with new bridge:

As concerns have been submitted regarding the new Columbia Road bridge truss and railing interrupting visibility of approaching east bound traffic from the south approach of Waverly Road at Columbia Road immediately east of the new bridge, the following information and links to related photos are provided:

When motorists stop in advance of the ‘STOP’ sign, the intersection visibility is more than adequate, and significantly improved from the conditions at the old bridge prior to tree clearing for construction of the new bridge (see before and after photos by clicking on the blue text of the words before and after). 

To emphasize the appropriate stop location, a new ‘STOP HERE’ sign was added (see photo) to emphasize that motorists should stop in advance of the ‘STOP’ sign and the stop bar on the pavement in order to see approaching eastbound Waverly Road traffic through the truss and railing.  From this vantage point, the visibility of vehicles approaching the bridge and on the bridge (viewed through the truss) can be clearly observed and motorists should readily be able to identify traffic gaps to safely enter Columbia Road (see video).

While the truss can obscure visibility from vehicles that stop beyond the stop bar, motorists can still pull up carefully on the new wider paved shoulder to the lane edge and see INSIDE the truss without impeding Columbia Rd traffic (see shoulder photo).

The attached photos and videos will help motorists who have had difficulty with visibility at the new bridge to comfortably and safely navigate the intersection.

A flashing warning system which detects traffic in both directions will be installed soon to assist drivers on both Columbia Road and northbound Waverly Road at Columbia Road in identifying conflicting traffic. 



See list below of other future major road projects.  Further information will be added for these and other future projects when further determined. 

2019 Projects: Funding TIP Total ICRD Match
Lake Lansing Road--Hagadorn Road to Saginaw Hwy (BL-69)
(resurface, re-stripe for two way center left turn lane with one through lane in each direction and non-motorized lanes on both sides, & add various turn lanes at Hagadorn Road & Park Lake Road intersections)
Urban STP & CMAQ $975,000 $222,000
Waverly Road – Lansing Road to St. Joseph Street (reconstruct) Urban STP & other $2,397,000 $441,000
       
2020 Projects:
Cedar Street – College Road to Circle Drive (resurface) Urban STP $1,121,000 $204,000
Okemos Road Bridges at Red Cedar River north of Mt. Hope Road--Replace with undivided 4 or 5 lane new bridge and related road work.  Existing northbound historic concrete arch bridge to be removed or left for non-motorized use per outcome of Environmental Assessment to be conducted in 2019. Local Bridge & other  $3,652,000 $120,000


                                                                                                                                                          








Okemos Road – Shawnee Trail to Clinton Street
(reconstruct to undivided 4 to 5 lane road, plus replace southbound bridge over Red Cedar River with single, two-way, four lane bridge, and leave existing northbound concrete arch bridge for pedestrian use if desired by the community)
STPU & NHPP
$3,200,000
$1.94M
NOTE: The $1.94M of match for Okemos Road will likely be offset by Local Bridge Program funding.

 
Okemos Road – Shawnee Trail to Clinton Street
(reconstruct to undivided 4 to 5 lane road, plus replace southbound bridge over Red Cedar River with single, two-way, four lane bridge, and leave existing northbound concrete arch bridge for pedestrian use if desired by the community)
STPU & NHPP
$3,200,000
$1.94M
NOTE: The $1.94M of match for Okemos Road will likely be offset by Local Bridge Program funding.